Key information

Title
A METHOD OF EXTENDING A CRANE TOWER ALONG A WIND TURBINE TOWER, AND RELATED APPARATUS
Application number
20220266
Case type
National
Status
02.09.2024 Patent meddelt (B1)
Filed
02.03.2022
Priority
16.08.2021 NO 20210981
Effective date
02.03.2022
Publicly available
17.02.2023
Next annual fee due
31.03.2027
Applicant
WIND SPIDER AS (NO)
Owner
WIND SPIDER AS (NO)
Inventor
Petter Vabø (NO) et al.
Agent
HÅMSØ PATENTBYRÅ AS (NO)
Granted
02.09.2024
Patent number
348133
Expiry date
02.03.2042

Abstract and drawing


Disclaimer: This text has been machine-scanned and may contain errors – please refer to "Publications" for legally binding content.
Methods are described for extending a crane tower along a wind turbine, assembling a crane tower, shortening a crane tower, and constructing a wind turbine tower, in addition to various related apparatus. In certain examples, a crane tower is supported upon the wind turbine tower and extended along the wind turbine tower, where the crane tower includes a crane at or near an upper end thereof, and the wind turbine tower is provided with apparatus including a lifter to elevate the crane tower to create space for inserting one or more extension sections at or near a crane tower base and adding them to the crane tower for extending the crane tower longitudinally along the wind turbine tower.

Publications


B1A1
Checking availability of the latest published version...

Documents


Expand Download files (30)
Date
Date Doc. No. Process Case number In/Out Journal description To/from
06.09.2024 14-01 Saksbehandling 20220266(348133) UT PT Registreringsbrev nasjonal patent (15) (PT20220266)
12.06.2024 13-01 Saksbehandling 20220266 UT Intention to grant HÅMSØ PATENTBYRÅ AS
07.05.2024 12-04 Saksbehandling 20220266 INN P30077NO01 Translated claims HÅMSØ PATENTBYRÅ AS
07.05.2024 12-03 Saksbehandling 20220266 INN P30077NO01 Letter to IPO HÅMSØ PATENTBYRÅ AS
07.05.2024 12-02 Saksbehandling 20220266 INN P30077NO01 Amended claims HÅMSØ PATENTBYRÅ AS
07.05.2024 12-01 Saksbehandling 20220266 INN Korrespondanse (Hovedbrev inn) HÅMSØ PATENTBYRÅ AS
25.04.2024 11-01 Saksbehandling 20220266 UT Substantive examination HÅMSØ PATENTBYRÅ AS
23.04.2024 10-06 Saksbehandling 20220266 INN P30077NO01 Letter to IPO HÅMSØ PATENTBYRÅ AS
23.04.2024 10-05 Saksbehandling 20220266 INN P30077NO01 Amended description HÅMSØ PATENTBYRÅ AS
23.04.2024 10-04 Saksbehandling 20220266 INN P30077NO01 Amended claims HÅMSØ PATENTBYRÅ AS
23.04.2024 10-03 Saksbehandling 20220266 INN P30077NO01 Additional sheets description mark-up HÅMSØ PATENTBYRÅ AS
23.04.2024 10-02 Saksbehandling 20220266 INN P30077NO01 Additional sheets claims mark-up HÅMSØ PATENTBYRÅ AS
23.04.2024 10-01 Saksbehandling 20220266 INN Korrespondanse (Hovedbrev inn) HÅMSØ PATENTBYRÅ AS
06.02.2024 09-01 Saksbehandling 20220266 UT PT Varsel om betaling av første årsavgift (3317) (PT20220266) HÅMSØ PATENTBYRÅ AS
07.01.2024 08-02 Saksbehandling 20220266 UT PT report 03:55:06
07.01.2024 08-01 Saksbehandling 20220266 UT Substantive examination HÅMSØ PATENTBYRÅ AS
08.09.2023 07-01 Saksbehandling 20220266 INN Korrespondanse (Hovedbrev inn) HÅMSØ PATENTBYRÅ AS
08.12.2022 06-04 Saksbehandling 20220266 INN P30077NO01 Letter to IPO 08.12 HÅMSØ PATENTBYRÅ AS
08.12.2022 06-03 Saksbehandling 20220266 INN P30077NO01 Amended claims HÅMSØ PATENTBYRÅ AS
08.12.2022 06-02 Saksbehandling 20220266 INN P30077NO01 Additional sheets claims mark-up HÅMSØ PATENTBYRÅ AS
08.12.2022 06-01 Saksbehandling 20220266 INN Korrespondanse (Hovedbrev inn) HÅMSØ PATENTBYRÅ AS
30.11.2022 05-01 Saksbehandling 20220266 INN Korrespondanse (Hovedbrev inn) HÅMSØ PATENTBYRÅ AS
30.09.2022 04-01 Saksbehandling 20220266 UT General letter patent HÅMSØ PATENTBYRÅ AS
03.03.2022 03-01 Saksbehandling 20220266 UT Informasjon til oppfinner Petter Vabø
03.03.2022 02-01 Saksbehandling 20220266 UT Informasjon til oppfinner Per Olav Haughom
02.03.2022 01-05 Saksbehandling 20220266 INN P30077NO01_Signert generalfullmakt HÅMSØ PATENTBYRÅ AS
02.03.2022 01-04 Saksbehandling 20220266 INN P30077NO01 Patent Specification HÅMSØ PATENTBYRÅ AS
02.03.2022 01-03 Saksbehandling 20220266 INN P30077NO01 Drawings HÅMSØ PATENTBYRÅ AS
02.03.2022 01-02 Saksbehandling 20220266 INN P30077NO01 Brev til Styret- Retten til oppfinnelsen HÅMSØ PATENTBYRÅ AS
02.03.2022 01-01 Saksbehandling 20220266 INN Søknadsskjema Patent HÅMSØ PATENTBYRÅ AS

Description, claims and drawings


Disclaimer: This text has been machine-scanned and may contain errors – please refer to "Publications" for legally binding content. Description
A METHOD OF EXTENDING A CRANE TOWER ALONG A WIND TURBINE TOWER, AND RELATED APPARATUSThe present invention relates in particular to the installation, construction and maintenance of wind turbines.A modern wind turbine generally comprises a tower upon which blades connected to a rotary hub are supported on an upper end. The blades are coupled to a generator through a shaft and bearings arrangement at the top of the tower. In use, the blades are caused to turn by the wind which in turn produces rotation of a shaft and allows electricity to be produced by the generator. In addition to the generator, auxiliary equipment, such as a transformer and control and monitoring systems, is typically provided. The top structure, referred to as a nacelle, is typically supported on the tower with bearings, so that the nacelle can be rotated around a vertical axis of the tower and be adjusted to varying wind directions. The blades are coupled to the nacelle.Wind turbines have developed from small land-based wind turbines of 200-300 kW to today's larger turbines of about 10 MW. Apart from differences of scale, the configuration of wind turbines has largely kept to the same general design over many years. Current developments include floating wind turbines capable of producing installed power of up to 15-20 MW.In today's wind turbines, the nacelle is typically built as an assembled structure which can then be hoisted onto the top of the tower structure when the tower structure has been assembled to its full height. Wind turbines of about 10 MW generally have a tower height of about 200 m and the nacelle can weigh 300-400 tonnes. A nacelle of 300-400 tonnes to be lifted about 200 m up typically requires large and expensive hoisting devices. Lifts of this kind can be particularly challenging in the case of floating wind turbines where the hoisting device on a floating base can be affected by wave movements. The time intervals for acceptable wave conditions are often very short. Installation of floating wind turbines can be technically highly demanding and costly.On land, the development of wind farms may impinge upon the surrounding infrastructure and environment. Access to installation sites on roads may be difficult and road networks may not be well suited for transporting wind turbine components and heavy cranes, especially where such components may be long and cumbersome, and especially to remote sites.The tower structure of a wind turbine is often cylindrical and installed by cylindrical tower sections which are bolted together. Thereafter, the nacelle and the blades are added. Tower climber devices may be employed for providing access and assisting with the assembly process. The climber device may typically travel up/down the tower and grip/release sections of the tower structure in the necessary locations along the tower structure as it climbs up/down. Climbers can thus involve technical complexity and operational limitations that may render them technically unsuitable or an unattractive option in some projects.In many designs, the sections of the tower structure are tapered toward the upper end. Thus, the tower to be constructed may be wider at the lower end and may gradually become narrower toward the upper end. This can pose significant difficulties in that the diameter changes along its length and different diameters need to be accommodated in different sections of the tower. Furthermore, different wind turbine towers may have a different angle of taper. The inventor has noted that the tapered configuration of the wind turbine tower can pose significant engineering difficulties which may prevent or hamper the effectiveness of existing solutions for assembly or maintenance of the wind turbine from being applied, as for example can be found in various solutions based upon climber devices.Amongst the aims and objectives of the present invention it is sought to obviate or at least mitigate one or more drawbacks of prior art.According to a first aspect of the invention, there is provided a method of extending a crane tower along a wind turbine tower, the method comprising the steps of: providing a crane tower to be extended along at least a portion of a wind turbine tower, the crane tower comprising one or more crane tower sections and a crane at or near an upper end of the crane tower, and providing support means and at least one lifter; locating the crane tower in a first position, in which a lower end of the crane tower is arranged at or near a crane tower base; using the lifter, elevating the crane tower away from the crane tower base toward a second, elevated position, thereby creating space for one or more crane tower extension sections to be inserted at or near the crane tower base; supporting the crane tower in the elevated position using the support means; arranging one or more crane tower extension sections in the created space; and adding the one or more crane tower extension sections to a lower end of the elevated crane tower, thereby extending the crane tower; wherein the wind turbine tower includes a foundation, and the crane tower is supported by at least a portion of the wind turbine tower or the foundation thereof, the weight of the crane tower at least partially transmitted to the wind turbine tower or the foundation thereof through the crane tower base.The method may further comprise one or more further features as set out in any of the dependent claims 2 to 27 of the claims appended hereto.The crane tower base may be or may comprise a platform. The platform may be connected to the wind turbine tower. The foundation may be a floating foundation. The foundation may be a bottom fixed offshore foundation, a floating foundation, or a ground supported foundation.According to a second aspect of the invention, there is provided apparatus for supporting a crane tower on a wind turbine tower, or on a foundation section of a wind turbine tower, and performing the method in accordance with any preceding claim, wherein the wind turbine tower or the foundation section thereof is provided with a crane tower base, the apparatus comprising: at least one crane tower section to extend around a wind turbine tower section; a crane device configured to be coupled to and supported on an upper end of the at least one crane tower section; a lifter device for advancing a crane tower, including the at least one crane tower section and the crane device, along the wind turbine tower between a first, base position in which a lower end of the crane tower is arranged at or near the crane tower base and a second, elevated position in which a lower end of the crane tower is elevated along the wind turbine tower with respect to the first position; support means for supporting the crane tower in the second, elevated position; and at least one crane tower extension section to extend around a wind turbine tower section; wherein the lifter device is configured to advance the crane tower, at least in a first mode of operation, away from the first position toward the second position to create space for inserting the at least one crane tower extension section into the created space for allowing the at least one crane tower extension section to be arranged in the space and connected to the crane tower in order to extend the crane tower.The apparatus may further comprise a crane tower base configured to be provided on the wind turbine tower or on the foundation section of the wind turbine tower.The support means may comprise or be a support frame.Typically, the lifter device comprises a carriage arranged to travel longitudinally to move the crane tower from the base position to the elevated location.The carriage may be hoisted or lowered on a winch line from a winch drum.The winch drum may be located on the platform. The winch line may be passed over a suspending member on the support frame.Locking the crane tower to the support means may be performed by locking the elevated crane tower to the support frame.The wind turbine tower may be an offshore wind turbine tower.The crane tower sections may be provided with one or more radial standoff arms extending in a radial direction to bear against an outer surface of the wind turbine tower for providing lateral standoff between the crane tower and the wind turbine tower.The apparatus may further comprise a winch having a winch wire, for operating the lifter device.Typically, the apparatus may include locking means to lock the crane tower in the elevated position to the support means. The lifter device may be disengageable from the locked crane tower in the elevated position.The wind turbine tower may be a floating wind turbine tower. The wind turbine tower may be a wind turbine tower as described anywhere else herein.Any of the various aspects of the invention may include further features as described in relation to any other aspect of the invention, wherever described herein. Embodiments of the various aspects of the invention may be advantageous in various ways as will be apparent herein throughout.There will now be described, by way of example only, embodiments of the invention, with reference to the accompanying drawings, in which:Figure 1 is a front representation of a fully constructed wind turbine;Figure 2 is a side representation of the wind turbine of Figure 1;Figure 3 is a perspective representation of a root portion of a wind turbine tower, in the process of installing apparatus for constructing the wind turbine tower, according to an embodiment of the invention;Figure 4 is a perspective representation of the root portion of the wind turbine tower, in the process of installing apparatus for constructing the wind turbine tower, at a further stage of the installation;Figure 5 is a close-up representation of the area D in Figure 4;Figure 6 is a close-up representation of the area A in Figure 4;Figure 7 is a perspective view of an part of the support frame of elevation means of the installed apparatus depicted in Figure 4 to extend around the root portion of the wind turbine tower; Figure 8 is a perspective view in close up of area B in Figure 4 showing an upper end of the root portion of the wind turbine tower with extendable gripper elements on the support frame of Figure 7;Figure 9 is a representation of the area C of Figure 8 showing one of the extendable gripper elements in close up;Figure 10 is a perspective representation of the root portion of the wind turbine tower, in the process of installing the apparatus for constructing the wind turbine tower at a yet further stage of the installation;Figure 11 is a perspective representation of a part of a tower section of the crane tower of the apparatus undergoing installation in Figure 10;Figure 12 is a close-up representation of the area A of Figure 10, showing detail including stand-off rollers on a tower section of the crane tower;Figure 13 is a close-up representation of the area B of Figure 10 showing detail including winch cable connection points for operating the lifter of the elevation means;Figure 14 is a close-up representation of the area C of Figure 12 showing one of the stand-off rollers in further detail;Figure 15 is a close-up representation of the area D of Figure 11 showing a formation extending around the an upper end of the part of the crane tower section for facilitating engagement with the gripper element of the elevation means;Figure 16 is a side representation of the root portion of the wind turbine tower of Figure 10 with the apparatus installed ready for further assembly of the wind turbine tower; Figure 17 is a side representation of the root portion of the wind turbine tower of Figure 16 with the crane of the crane tower of the apparatus positioning a further wind turbine tower section above the upper end of the root portion of the wind turbine tower for connection thereto to extend the wind turbine tower, in the construction of the wind turbine tower;Figure 18 is a side representation of the wind turbine tower under construction the further section of Figure 17 having been connected, and after lifting the crane tower upwards along the wind turbine tower using the elevation means of the apparatus;Figure 19 is a side representation of the wind turbine tower of Figure 18 under construction, after lowering the lift of the elevation means and after arranging elements of an extension section of the crane tower around the wind turbine tower, below the lower end of the elevated crane tower;Figure 20 is a close-up representation of the area B of Figure 18 showing the lifter of the elevation means and elevated tower section in an elevated position;Figure 21 is a perspective representation of a part of the extension section of the crane tower provided around the wind turbine tower in Figure 19;Figure 22 is a part of the carriage of the lifter to extend around the support frame of the elevation means and around the root portion of the wind turbine tower as seen in installed apparatus of preceding figures;Figure 23 is side representation of the wind turbine under construction at a stage further from that of Figure 19, after positioning a yet further tower section of the wind turbine tower above an upper end of the installed portion of the wind turbine tower and connecting the yet further tower section thereto, and after lifting the crane tower upwards along the installed portion of the wind turbine tower;Figure 24 is a sectional side representation of the wind turbine tower under construction at the stage of Figure 23, along the line D-D of Figure 23;Figure 25 is a close up of an engager of the elevation means in locking engagement with a tower section of the crane tower for locking or holding the crane tower in elevated position;Figure 26 is a perspective view of the wind turbine tower under construction at the stage of Figure 23;Figure 27 is a cross sectional representation of the tower under construction with the apparatus along the line C-C of Figure 23;Figure 28 is a side representation of the wind turbine under construction, after a further extension section of the crane tower is connected and inserted to extend the crane tower which is supported on the root portion of the wind turbine on a platform extending radially and around the root portion, the wind turbine tower having been assembled using the crane tower, the nacelle having been connected to the upper end of the wind turbine tower, and with a rotor blade being lifted upwards for arranging the blade for connection to the nacelle; andFigure 29 is a perspective view of the wind turbine under construction at the stage of Figure 28; andFigure 30 is a close-up view of the area A of Figure 28 showing the coupling of the blade to a counterweighted lifting yoke.Referring first to Figures 1 and 2, a fully constructed wind turbine 1 is depicted. The wind turbine 1 has wind turbine tower 100 including a root portion 101 comprising a foundation 8 and a lower tower section 2. The foundation 8 can vary in form depending for example upon whether the wind turbine is a floating wind turbine, a fixed seabed wind turbine, or a land wind turbine. The present example is for illustrative purposes a floating wind turbine 1, with the root portion 101 extending through the surface of the water (not shown). At least the lower part of the foundation 8 is submerged and the lower tower section 2 extends vertically upward from the sea surface. The construction of the wind turbine 1 as will be explained further below involves first installing the root portion 101. The remainder of the wind turbine 1 is then constructed using apparatus supported upon the root portion 101.As can be appreciated in Figures 1 and 2, the wind turbine tower 100 includes in the upward direction from the foundation 8 a tower section 2, a further tower section 3, and a yet further tower section 4. In this example, just three tower sections are provided, not counting the foundation 8. The tower sections 2, 3, 4 are elongate frustoconical tapered sections that connect one to the other endto-end at connecting joints 29. The resulting tower 100 between the foundation 8 gradually tapers, i.e. reduces in outer diameter toward the upper end.A nacelle 6 is arranged on an upper end of the wind turbine tower 100. Three blades 7 are connected to a hub 45 on the nacelle 6 having an axis of rotation typically horizontal or near horizontal in use. The blades 7 connect at connection points spaced apart around the hub at equal angle intervals. The blades 7 extend radially away from the hub of the nacelle 6. The set of blades 7 rotate about the axis of rotation for turning a shaft and driving a generator in the nacelle 6.The construction of the wind turbine 1 will now be described. The construction of the wind turbine 1 is facilitated by apparatus which is installed and supported on the root portion 101 of the wind turbine tower 100 and which includes a crane 201 that is supported at an upper end of a crane tower 200. The crane tower 200’ can be extended along the wind turbine tower 100 in stages as the wind turbine tower is assembled. The apparatus includes a base for the crane tower and extended crane tower in the form of a platform 10 on the root portion 101 of the partially constructed wind turbine tower 100. The apparatus also includes elevation means 300 including a lifter for lifting the crane tower 200 upward along the wind turbine tower 100 to an elevated position, and creating insertion space for inserting a crane tower extension sections 30 between the platform and the elevated crane tower 200 and adding the extension section 30 to the crane tower. Once added, the reach of the extended tower 200’ attainable from the base platform 10 is greater, so that the crane 201 can be employed for assisting with assembling a further wind turbine tower section to the wind turbine tower.The construction of the wind turbine 1 can therefore be considered to include several stages:i. providing the root portion 101;ii. installing the elevation means 300 on the root portion 101 (Figures 3 to 9);iii. installing the crane tower 200 of first length (which later is to be extended to greater length), providing the crane tower 200 with a crane 201 on an upper end thereof, the crane tower 200 to be supported upon the platform on the root portion 101, with a crane tower section 20 extending circumferentially around the root portion (Figures 10 to 16);iv. extending the crane tower 200, the extended crane tower 200’ having a second length that is greater than the first length, using the crane 201 to add one or more further wind turbine tower sections 3, 4 to the wind turbine tower 100, the elevation means 300 being used to elevate the crane tower 200 and allow extension sections 30, 40 to be added to the crane tower 200 (Figures 17 to 27); andv. using the crane 201 once the crane tower 200 has been fully extended, having a length extending from the platform 10 on root portion 101 to the upper end of the top tower section of the full length wind turbine tower 100, lifting the nacelle 6 to the upper end of the wind turbine tower 100 for connection thereto, and lifting the wind turbine blades 7 one by one to position the lifted blade 7 adjacent to the nacelle 6 for connection thereto (Figures 28 to 30). The crane 201 can also be used for modification and maintenance operations on already constructed wind turbines. In those cases, the steps i. to iv. is carried out to extend the crane tower along the wind turbine tower, but without adding further wind turbine tower sections to the wind turbine tower 100 since it is already constructed. Once the crane 201 has been raised to the desired height, the crane 201 can be used to for example remove and replace one or more blades, or parts of the nacelle.After the wind turbine 1 has been constructed, the fully extended crane tower 200’’ is dissembled by using the elevation means 300 to hold the crane tower 200’’ in position while decoupling and removing the lower crane tower extension section 40 of the crane tower 200, thereby shortening the crane tower, supporting and lowering the shortened crane tower 200’ from the elevated position to a lowered position, holding the crane tower 200’ in position using the elevation means 300, decoupling and removing the next extension section 30, further lowering the crane tower 200, etc.As the crane tower 200 is built by from time to time inserting and adding extension sections in created space between the platform 10 and crane tower to be extended, and by using equipment installed upon the platform or root portion to provide the necessary manipulation of the crane tower to create the space to insert and add the extension sections, the crane tower can be raised upward having cylindrical tower framework spaced apart from the further wind turbine tower sections 3, 4 and joints 29 to be assembled, without requiring to engage those further sections 3, 4 in weight bearing relationship. Accordingly, the construction technique of building the crane tower 200 “bottom up” from the platform or defined base location upon the initially installed root portion, can be well suited for applications where tower sections 3, 4 of the wind turbine tower 100 are tapered. It may also be convenient in general for all wind turbine types, but in particular those offshore.Turning then to Figures 3 to 9, the method of installing the elevation means 300 is now further described. The elevation means 300 includes a lifter which in this example is in the form of a carriage 11 operable by winches 15. The root portion 101 of the wind turbine tower 100 includes the foundation 8 and a longitudinally extending section 2 of the wind turbine tower, which are pre-installed at the installation site. The root portion 101 is provided with a base for the crane tower in the form of a platform 10 on the root portion. The platform 10 extends circumferentially around the root portion 101. The platform 10 extends radially outward with respect to an outer surface of the wind turbine tower section 2. The platform 10 has work deck or floor for operators. The platform 10 is rigidly and fixedly mounted on the root section in desired location.The carriage 11 is arranged on the platform 10. The platform 10 has supports or a seat against which the carriage 11 rests in certain modes of use, as will be further described below. The winches 15 are also arranged on the platform 10. The carriage 11 comprises a frame which extends ring-wise around the tower section 2 of the wind turbine tower. The carriage 11 is assembled by connecting frame parts of the supporting frame to one another. The carriage 11 is arranged to be movable upward, away from the platform 10, and/or downward, toward the platform 10 along the tower section 2 of the root portion 101.The elevation means 300 further includes support means in the form an elevation support frame 13 which extends around the tower section 2 in the root portion of the wind turbine tower. Parts of the elevation support frame 13 are arranged in an annular space between an inside of the frame of the carriage 11 and the outer surface of the tower section 2. The parts are connected to obtain the support frame 13 that is cylindrical and extends circumferentially around the wind turbine tower section 2. The elevation support frame 13 extends longitudinally along the tower section 2. The carriage 11 is arranged also to extend around the elevation support frame 13. The elevation support frame 13 is fixedly provided on the platform, and the platform 10 is fixedly provided upon the root portion of the wind turbine tower. Thus, the carriage 11 is movable upward/downward along the elevation support frame 13.The elevation support frame 13 is a straight non-tapered cylindrical frame extending upward from the platform 10, whereas the tower section 2 tapers toward the upper end.On the upper end of the support frame 13, disposed circumferentially thereupon with equal angular spacings and in different locations around the frame, locking means comprising engager devices 19 which have extendable members 18 are provided. The extendable members 18 are operable to extend outwardly from a housing to engage with a corresponding formation or member of a crane tower section of the elevated crane tower (to be described further below), so as to be capable of temporarily supporting the crane tower on the support frame 13 and locking against movement between the crane tower in the elevated position and the support frame.The upper end of the support frame 13 is also provided with guides 17 for receiving the cables 15w from the respective winches 15. The cable 15w of each winch 15 extends from the winch 15 upward along an inside of the support frame 13, outward over the guides 17 and downward along an outside of the support frame 13 to the carriage 11 where the end of the cable 15w is attached to fastening lugs 14 on the carriage 11. Three winches 15 are fixedly installed on the platform 10, the cables 15w from the winches 15, pass under three lower guides, upward over the three guides 17, and connect to corresponding three lugs 14 on the carriage 11. Thus, by pulling in the cables in the direction as indicated by arrows A using the winches 15, the cable 15w from each winch 15 acts to pull the carriage 11 upward along the support frame 13. The three winches 15 can help to cope with large loads, distribute force and provide redundancy if one should break.Turning then to Figures 10 to 16, steps of providing and arranging the crane tower 200 in an initial configuration, before the crane is used for work in assembling the wind turbine tower, are now described. The crane tower 200 comprises a crane 201 and a crane tower section 20. Parts of the crane tower section 20 are arranged around the wind turbine tower and are coupled together. The crane tower section 20 is in the form of an elongate cylindrical frame which extends alongside the tower section 2 of the wind turbine tower. The frame is a straight cylinder. The crane tower section 20 is arranged so as to extend around the support frame 13 of the previously assembled elevation means 300. The crane 201 has a crane base 22 that is connected to an upper end of the crane tower section 20. The lower end of the crane tower section 20 is supported upon the carriage 11. The weight of the crane tower 200 including the crane 201 is supported and transferred through the tower section section 20 and the carriage 11 and through the platform 10 to the root portion 101 of the wind turbine tower. The cylindrical frame of the crane tower section 20 has diametric match with the support frame of the carriage 11 which in turn rests supportingly upon the platform 10. Force imparted through the weight of the crane tower is transferrable therefore directly downwards vertically through the matching frames of the tower section 20 and the carriage 11, and the platform 10 to the root portion 101, and can provide a strong and materials efficient construction of the crane tower 200. In this configuration, the crane tower 200 is arranged in a base position, and the crane is operable in work mode for adding a further wind turbine tower section to the partially constructed wind turbine tower.The crane 201 has an A-frame or inverted U or V frame boom 24 which is pivotally coupled to the crane base 22. The crane base is in the form of a ring and has an opening corresponding in diameter to diameter of the crane tower section 20. The opening allows access to the upper end of the partially constructed wind turbine tower. The boom 24 has legs rising upward either side of the crane base 22 and a transverse beam between the upper ends of the legs for bridging across and positioning top guide 27 for the crane wire 26w over the opening. The boom 24 is arranged to pivot about a horizontal axis X under control of linear hydraulic actuator cylinders 23 which act between the crane base 22 and the legs 24a, 24b of the boom 24. The crane 201 is also rotatable around a vertical axis on the crane base 22.A crane winch 26 is provided on the platform 10 and the wire 26w from the crane winch 26 is passed through guide 25 on an arm extending radially outwardly from the crane base 22 of the crane 201 and passed onward upwardly from the guide 25 over the top guide 27 on the boom 24 for suspending loads 28 on the wire 26w over the top guide 27 from the boom 24. The boom 24 is configured to have a reach upward from the crane base 22 exceeding the length of the further tower sections 3, 4, to be added to the wind turbine tower. In this way, the boom 24 can suspend a further tower section 3, 4 that needs to be added in upright orientation over the upper end of the partially constructed tower, and can lower the tower section 3, 4 through the opening onto the upper end, by paying out the wire 26w.The crane base 22 is provided with stand-off members 41 which protrude radially inwardly at distributed locations around an inside circumference of the crane base 22. In other variants, stand-off members 41 are alternatively or additionally provided on the crane tower sections 20, 30, 40 of the crane tower. The stand-off members 41 can facilitate centralisation of the crane tower 200 with respect to the wind turbine tower 100. They can provide stand-off between the crane tower 200 and the wind turbine tower 100 under construction in the event of adverse forces. They can facilitate proper positioning of the crane tower 200 with respect to the wind turbine tower under construction, which may help positioning the crane tower 200 when assembling and connecting further extension tower sections 30, 40 to the crane tower 200 and further tower sections 3, 4 to the wind turbine tower 100. The stand-off members 41 each comprises a spring-loaded arm which is biased to pivot inwardly to adapt to varying distances between the outer surface of the wind turbine tower and the crane tower, and the distance may vary and become larger toward the upper end of the wind turbine tower due to the upward taper. The stand-off members 41 each have a roller wheel 42 on the end of the arm for contacting an outer surface of the installed portion of the wind turbine tower under construction. The roller wheels 42 roll on the outer surface of the wind turbine tower upon lifting the crane tower 200 upward along the wind turbine tower 100 into the elevated position.Turning now to Figures 17 to 27, the steps of extending the length of the crane tower upward from the root portion, using the crane to add one or more further tower sections to the wind turbine tower, using the elevation means being to elevate the crane tower and allow further support sections of the crane tower to be added to the crane tower to obtain an extended reach from thee platform 10 is now further described.The crane 201 is first used in work mode to suspend a further tower section 3 on the wire 26w over an upper end of the tower section 2 of the partially constructed wind turbine tower. Once positioned, the tower sections 2, 3 are connected to one another, end-to-end, thereby lengthening the wind turbine tower.It is then sought to position the crane 201 at the upper end of the further tower section 3 and connect a yet further tower section 4 to the wind turbine tower. For this purpose, the crane tower 200 is extended, by insertion of a crane tower extension section in created space around the root portion 101 at or near the platform 10 and connecting the tower extension section 30..The elevation means 300 is then used. More specifically, the carriage 11 is operated (by the winches 15) so that it is moved upward along the elevation support frame 13 and along the tower section 2 of the root portion 101 of the wind turbine tower. The carriage 11 is operated by activating the winches 15 to pull in the winch cables 15w. The crane tower 200 to be extended is driven and translated linearly and axially upward on the carriage 11. At the end of the travel, the crane tower 200 obtains an elevated position, and the engager members 19 of the locking means are operated for locking the crane tower to the elevation support frame 13, whereby the end members 18 engage with a circumferential groove formation 31 of the parts 21 of the crane tower section 20. By operation of the engagers 19, the end 18 is urged into the grove formation 31, and the elevated crane tower 200 is fixedly held with respect to the elevation support frame 13 of the elevation means 300. While being held in place by the engages, the carriage 11 is decoupled from the tower, and returned downward to the platform by operation of the winches 15. Space is created between the carriage 11 and the crane tower in the elevated position, when the carriage 11 is seated back upon the platform 10.The extension section 30 of the crane tower 200 is then assembled. Parts 21’ of the extension section 30 are arranged in the created space around the tower section 2 of the wind turbine tower 100 and are coupled together. The extension section 30 is in the form of an elongate cylindrical frame which extends along the tower section 2 of the wind turbine tower. The frame is a straight cylinder. The extension section 30 is arranged so as to also extend around the elevation support frame 13 of the previously assembled elevation means 300. The lower end of the extension section 30 is arranged to be supported upon the carriage 11 resting upon the platform 10.The upper end of the extension section 30 is coupled, end-to-end to the lower end of the crane tower section 20 of the crane tower in the elevated position. The lower end of the extension section 30 is supported upon the carriage 11. In this way, the addition of the further extension section 30 to the crane tower 200 extends the length of the crane tower 200 along the partially constructed wind turbine tower 100. After the extension section 30 is added, the engagers 19 are disengaged from the crane tower, unlocking it from the elevation frame 13, for permitting further extension of the crane tower. Forces imparted by the crane 201 and loads suspended therefrom e.g. during lifts of wind turbine tower sections or other components of the wind turbine to be installed, are transferred and supported directly through the end to end connected crane tower section 20, extension section 30, carriage 11 and platform 10 to the root portion 101 of the wind turbine tower 100. No further load-bearing connection to the wind turbine tower 100 is required.The crane 201 is then used as seen in Figure 19 to suspend and position the yet further tower element 4 above the upper end of previously installed tower section 3 of the wind turbine tower 100. The yet further wind turbine tower section 4 is installed in the same way as described above for the tower section 3.Then, as seen in Figure 23, after the yet further tower section 4 is connected onto the end of the partially constructed wind turbine tower 100 thereby extending it further, the elevation means 300, in particular the carriage 11 and engagers 19, are once again employed to elevate the lengthened crane tower 200’ to an elevated position. In the elevated position, the crane base 22 is positioned near the top of the yet further wind turbine tower section 4 for allowing the crane 201 access to the upper end of the further tower section 4. Insertion space is created around the tower section 2 of the root portion of the wind turbine tower for inserting a further crane extension section 40 in the created space between crane tower 200’ and the platform 10. The engagers 19 on the elevation support frame 13 engage the extension tower section 30 to hold the lengthened crane tower 200’ in the elevated position whilst the further extension section 40 is arranged around the section 2 of the wind turbine tower and are connected in the same way as described above in relation to earlier extension section 30 of the crane tower.Turning to Figures 28 to 30, the crane tower 200’’ is fully extended with the crane 201 arranged to access the upper end the wind turbine tower 4. The wind turbine tower 100 is assembled to full length. The crane extension section 30 and further crane extension section 40 are incorporated so that the crane tower has attained full reach along the wind turbine tower 100 from the platform with the base at the top end of the wind turbine tower. The crane tower 200 is supported through the extension sections 30, 40, the carriage 11 and platform 10 to the root portion 101 of the wind turbine tower 100.In this configuration, the crane 201 in use mode is then used for the lifting and assembly of the further components of the wind turbine 1, in particular the nacelle 6 and the blades 7. The nacelle 6 is installed on rotatable base on an upper end of the wind turbine tower in the space between legs of the boom 24. The blades 7 are hoisted up to the top of the tower on the crane wire 26w of the crane 201.The end of the crane wire 26w is connected to a rod 39 which is suspended vertically from the boom 24 and the rod 39 in turn is connected to a lifting beam 37 extending transverse, i.e. horizontally, to the rod 39. The wind turbine blade 7 is coupled to one end of the lifting beam 37 via a mount 36 and obtains a horizontal orientation so that a longitudinal axis of the turbine blade 7 is horizontal to a longitudinal horizontal axis of the beam 37. The other end of the beam 37 is counterweighted by a counterweight 38. The blade 7 can by spooling in the length of wire 36w suspended from boom 24 therefore be manoeuvred and positioned near the hub 45 of the nacelle 6 in suitable orientation for connection of the connecting end of the blade 7 to the hub 45. The crane can be rotatable about a vertical axis Y upon the crane base 22.After the blades 7 have all been connected, the crane 201 and crane tower 200’’ is lowered and disassembled by carrying out the steps for extending and elevating the crane tower in reverse order. Thus, the crane tower 200’’ can be shortened and lowered by removal of the bottom extension section 40 whilst the remainder of the crane tower 200’ from which the extension section 40 is removed is supported and locked in position to the elevation support frame 13 by the engagers 19. The crane boom 24 is positioned so as to leave the opening of the crane base 22 unobstructed, allowing the lowering of the crane tower with the wind turbine extending through the opening. The elevation means 300 and platform 10 are removed from the root portion 101 of the wind turbine tower, and the fully constructed wind turbine 1 as depicted in Figures 1 and 2 is obtained. The crane 201 and the crane tower 200 can be used to perform various modification and maintenance operations, such as removing and/or replacing one or more blades 7 or removing and/or replacing the whole or portions of the nacelle 6, such as a gear or a generator. In this case, the crane tower 200 is installed and lengthened along an existing wind turbine tower. When the crane 201 reaches the desired height, the desired lifting operation can be performed by using the crane 201 on the extended crane tower 200.In some variants, the assembly process starts with lifting and installing a unit comprising a tower section with the platform, support means, and lifter attached, onto the foundation. The crane is thereafter arranged on the lifter.Various modifications and improvements may be made without departing from the scope of the invention herein described.
Claims
CLAIMS1. A method of extending a crane tower (200) along a wind turbine tower (100), the method comprising the steps of:providing a crane tower (200) to be extended along at least a portion of a wind turbine tower (100), the crane tower (200) comprising one or more crane tower sections (20) and a crane (201) at or near an upper end of the crane tower (200), and providing support means (13) and at least one lifter (11);locating the crane tower (200) in a first position, in which a lower end of the crane tower (200) is arranged at or near a crane tower base (10);using the lifter (11), elevating the crane tower (200) away from the crane tower base (10) toward a second, elevated position, thereby creating space for one or more crane tower extension sections (30) to be inserted at or near the crane tower base (10);supporting the crane tower (200) in the elevated position using the support means (13);arranging one or more crane tower extension sections (30) in the created space; andadding the one or more crane tower extension sections (30) to a lower end of the elevated crane tower (200), thereby extending the crane tower (200);wherein the wind turbine tower (200) includes a foundation (8), and the crane tower (200) is supported by at least a portion of the wind turbine tower (100) or the foundation (8) thereof, the weight of the crane tower (200) at least partially transmitted to the wind turbine tower (100) or the foundation (8) thereof through the crane tower base (10).2. A method as claimed in claim 1, which further comprises:locating the crane tower (200) in the base position, in which a lower end of the extended crane tower (200) is arranged at or near the crane tower base (10);operating the lifter (11) to elevate the extended crane tower (200) away from the crane tower base (10) toward an elevated position, thereby creating space for one or more further crane tower extension sections (40) to be inserted at or near the crane tower base (10);locating and supporting the extended crane tower (200) in the elevated position;arranging one or more further crane tower extension sections (40) in the created space in the area around the wind turbine tower (100); and adding the one or more further crane tower extension sections (40) to a lower end of the elevated crane tower (200), thereby further extending the crane tower (200).3. A method as claimed in claim 1 or 2, comprising the steps of:locating the extending crane tower (200) in the base position, in which a lower end of the extending crane tower (200) is arranged at or near the crane tower base (10); andusing the crane (201) on the extending crane tower (200) to perform a lifting operation.4. A method as claimed in any preceding claim, wherein the crane tower base (10) is supported on the wind turbine tower (100) or on a foundation (8) of the wind turbine tower (100).5. A method as claimed in claim 4, wherein the foundation (8) comprises any one or more of: a floating foundation, a bottom fixed offshore foundation, a ground supported foundation.6. A method as claimed in any preceding claim, wherein the crane tower base (10) comprises a platform structure extending outwardly from the wind turbine tower (100) or from a foundation (8) of the wind turbine.7. A method as claimed in any preceding claim, wherein the support means (13) comprises a support frame, and the method includes connecting at least two components to assemble the support frame which extend circumferentially at least partially around a portion of the wind turbine tower (100).8. A method as claimed in any preceding claim, wherein the lifter (11) comprises a carriage arranged to travel longitudinally to move the crane tower (200) from the first position to the second, elevated position.9. A method as claimed in any preceding claim, wherein the lifter (11) is arranged to extend circumferentially at least partially around a portion of the wind turbine tower (100).10. A method as claimed in any preceding claim, wherein the support means (13) comprises support frame which extends in a circumferential direction at least partially around a portion of the wind turbine tower (100), and the lifter (11) is arranged to extend circumferentially at least partially around an outside of the support frame, whereby a lower end crane tower section (20, 30, 40) of the tower (200) being elevated is arranged in abutment upon an upward facing surface of the support frame, and is engaged by the carriage, the carriage being movable up/down along the support frame.11. A method as claimed in any preceding claim, wherein the weight of the support means (13) is at least partially transmitted to the crane tower base (10).12. A method as claimed in any preceding claim, wherein supporting the crane tower (200) in the second, elevated position, comprises locking the crane tower (200) to the support means (13).13. A method as claimed in any preceding claim, wherein the wind turbine tower (100) comprises at least one wind turbine tower section (2, 3, 4).14. A method as claimed in any preceding claim, which further comprises operating the crane (201) to locate and position a wind turbine tower section (3, 4) in longitudinal orientation above an upper end of a previously installed wind turbine tower section (2, 3) of the wind turbine tower, and connecting the wind turbine tower section (3, 4) to the upper end.15. A method as claimed in any preceding claim, which further comprises operating the crane (201) to locate and position the whole or at least a part of a nacelle (6) above an upper end of a wind turbine tower section (2, 3, 4) for connection thereto.16. A method as claimed in any preceding claim, which further comprises operating the crane (201) to lift a wind turbine blade (7) adjacent to the nacelle (6) for connection thereto.17. A method as claimed in any preceding claim, which further comprises operating the crane (201) to either or both remove and replace parts of a wind turbine.18. A method as claimed in any preceding claim, wherein the crane (201) is operated to either or both remove and replace at least one of a blade (7) and parts of or the whole of the nacelle (6).19. A method as claimed in any preceding claim, which further comprises operating the crane (201) to perform at least one of a wind turbine installation operation and a wind turbine maintenance operation.20. A method as claimed in any preceding claim, which further comprises connecting at least two parts to assemble the crane tower extension section or sections (30, 40), which extend circumferentially at least partially around a portion of the wind turbine tower (100).21. A method as claimed in any preceding claim, wherein the one or more crane tower extension sections (30, 40) are cylindrical sections arranged to extend around and longitudinally along a portion of the wind turbine tower (100).22. A method as claimed in any preceding claim, which further comprises connecting at least two parts to assemble the crane tower section or sections (20, 30, 40), which extend at least partially around a portion of the wind turbine tower (100).23. A method as claimed in any preceding claim, wherein the one or more crane tower sections (20, 30, 40) are cylindrical sections arranged to extend around and longitudinally along a portion of wind turbine tower (100).24. A method as claimed in any preceding claim, which further includes connecting the crane tower extension section (30; 40) fixedly to a lower end tower section (20; 30) of the crane tower (200).25. A method as claimed in any preceding claim, wherein the wind turbine tower (100) is an offshore wind turbine tower.26. A method as claimed in any preceding claim, wherein the crane tower (200) to be extended is preinstalled.27. A method as claimed in any preceding claim, wherein the wind turbine tower (100) is an offshore wind turbine tower.28. Apparatus for supporting a crane tower (200) on a wind turbine tower (100), or on a foundation section (8) of a wind turbine tower (100), and performing the method in accordance with any preceding claim, wherein the wind turbine tower (100) or the foundation section (8) thereof is provided with a crane tower base (10), the apparatus comprising:at least one crane tower section (20) to extend around a wind turbine tower section (2, 3, 4);a crane device (201) configured to be coupled to and supported on an upper end of the at least one crane tower section (20);a lifter device (11) for advancing a crane tower (200), including the at least one crane tower section (20) and the crane device (201), along the wind turbine tower (100) between a first, base position in which a lower end of the crane tower (200) is arranged at or near the crane tower base (10) and a second, elevated position in which a lower end of the crane tower (200) is elevated along the wind turbine tower (100) with respect to the first position; support means (13) for supporting the crane tower (200) in the second, elevated position; andat least one crane tower extension section (30, 40) to extend around a wind turbine tower section (2, 3, 4);wherein the lifter device (11) is configured to advance the crane tower (200), at least in a first mode of operation, away from the first position toward the second position to create space for inserting the at least one crane tower extension section (30, 40) into the created space for allowing the at least one crane tower extension section (30, 40) to be arranged in the space and connected to the crane tower (200) in order to extend the crane tower (200).29. Apparatus as claimed in claim 28, further comprising a crane tower base (10) configured to be provided on the wind turbine tower (100) or on the foundation section (8) of the wind turbine tower (100).PATENTKRAV1. Fremgangsmåte for å forlenge et krantårn (200) langs et vindturbintårn (100), idet fremgangsmåten omfatter trinnene:å tilveiebringe et krantårn (200) som skal forlenges langs i det minste et parti av et vindturbintårn (100), idet krantårnet (200) omfatter én eller flere krantårnseksjoner (20) og en kran (201) på eller i nærheten av en øvre ende av krantårnet (200), og tilveiebringe støttemiddel (13) og minst én løfter (11);å lokalisere krantårnet (200) i en første posisjon, hvori en nedre ende av krantårnet (200) er anordnet på eller i nærheten av en krantårnbase (10);ved anvendelse av løfteren (11), å heve krantårnet (200) bort fra krantårnbasen (10) mot en andre, hevet posisjon, og derved skape rom til at én eller flere krantårnekstensjonsseksjoner (30) kan føres inn ved eller i nærheten av krantårnbasen (10);å støtte krantårnet (200) i den hevede posisjonen ved anvendelse av støttemiddelet (13);å anordne én eller flere krantårnekstensjonsseksjoner (30) i rommet som er skapt; ogå legge til den ene eller flere krantårnekstensjonsseksjonene (30) på en nedre ende av det hevede krantårnet (200), og derved forlenge krantårnet (200);hvor vindturbintårnet (200) inkluderer et fundament (8), og krantårnet (200) støttes av i det minste et parti av vindturbintårnet (100) eller fundamentet (8) derav, idet vekten av krantårnet (200) overføres i det minste delvis til vindturbintårnet (100) eller fundamentet (8) derav gjennom krantårnbasen (10).2. Fremgangsmåte ifølge krav 1, som videre omfatter:å lokalisere det forlengede krantårnet (200) i baseposisjonen, hvori en nedre ende av det forlengede krantårnet (200) er anordnet ved eller i nærheten av krantårnbasen (10);å betjene løfteren (11) for å heve det forlengede krantårnet (200) bort fra krantårnbasen (10) mot en hevet posisjon, og derved skape rom til at én eller flere ytterligere krantårnekstensjonsseksjoner (40) kan føres inn ved eller i nærheten av krantårnbasen (10);å lokalisere og støtte det forlengede krantårnet (200) i den hevede posisjonen; å anordne én eller flere ytterligere krantårnekstensjonsseksjoner (40) i rommet som er skapt i området rundt vindturbintårnet (100); ogå legge til den ene eller flere ytterligere krantårnekstensjonsseksjonene (40) på en nedre ende av det hevede krantårnet (200), og derved forlenge krantårnet (200) ytterligere.3. Fremgangsmåte ifølge krav 1 eller 2, omfattende trinnene:å lokalisere det forlengede krantårnet (200) i baseposisjonen, hvori en nedre ende av det forlengede krantårnet (200) er anordnet ved eller i nærheten av krantårnbasen (10); ogå anvende kranen (201) på det forlengede krantårnet (200) for å utføre en løfteoperasjon.4. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor krantårnbasen (10) er støttet på vindturbintårnet (100) eller på et fundament (8) av vindturbintårnet (100).5. Fremgangsmåte ifølge krav 4, hvor fundamentet (8) omfatter én eller flere av: et flytende fundament, et bunnfast offshore-fundament, et bakkestøttet fundament.6. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor krantårnbasen (10) omfatter en plattformstruktur som strekker seg utover fra vindturbintårnet (100) eller fra et fundament (8) av vindturbinen.7. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor støttemiddelet (13) omfatter en støtteramme, og fremgangsmåten inkluderer å koble sammen minst to deler for å sette sammen støtterammen som strekker seg periferisk i det minste delvis om et parti av vindturbintårnet (100).8. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor løfteren (11) omfatter en vogn anordnet til å vandre langsgående for å flytte krantårnet (200) fra den første posisjonen til den andre, hevede posisjonen.9. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor løfteren (11) er anordnet for å strekke seg periferisk i det minste delvis om et parti av vindturbintårnet (100).10. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor støttemiddelet (13) omfatter en støtteramme som strekker seg i en periferisk retning i det minste delvis om et parti av vindturbintårnet (100), og løfteren (11) er anordnet til å strekke seg periferisk i det minste delvis om en utside av støtterammen, hvorved en krantårnseksjon (20, 30, 40) på nedre ende av tårnet (200) som heves, er anordnet anliggende mot en oppadvendt overflate av støtterammen, og er satt i inngrep av vognen, idet vognen kan flyttes opp/ned langs støtterammen.11. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor vekten av støttemiddelet (13) overføres i det minste delvis til krantårnbasen (10).12. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor å støtte krantårnet (200) i den andre, hevede posisjonen omfatter å låse krantårnet (200) til støttemiddelet (13).13. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor vindturbintårnet (100) omfatter i det minste én vindturbintårnseksjon (2, 3, 4).14. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å betjene kranen (201) for å lokalisere og posisjonere en vindturbintårnseksjon (3, 4) i langsgående orientering over en øvre ende av en tidligere montert vindturbintårnseksjon (2, 3) av vindturbintårnet, og koble vindturbintårnseksjonen (3, 4) til den øvre enden.15. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å betjene kranen (201) for å lokalisere og posisjonere hele eller i det minste en del av et maskinhus (6) over en øvre ende av en vindturbintårnseksjon (2, 3, 4) for kobling dertil.16. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å betjene kranen (201) for å løfte et vindturbinblad (7) tilgrensende maskinhuset (6) for kobling dertil.17. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å betjene kranen (201) for enten eller både å fjerne og erstatte deler av en vindturbin.18. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor kranen (201) betjenes for enten eller både å fjerne og erstatte minst én av et blad (7) og deler av eller hele maskinhuset (6).19. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å betjene kranen (201) for å utføre minst én av vindturbinmonteringsarbeid og vindturbinvedlikeholdsarbeid.20. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å koble sammen minst to deler for å sette sammen krantårneksten sjonsseksjonen eller -seksjonene (30, 40), som strekker seg periferisk i det minste delvis om et parti av vindturbintårnet (100).21. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor den ene eller flere krantårnekstensjonsseksjonene (30, 40) er sylindriske seksjoner anordnet for å strekke seg om og langsgående langs et parti av vindturbintårnet (100).22. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre omfatter å koble sammen minst to deler for å sette sammen krantårnseksjonen eller -seksjonene (20, 30, 40), som strekker seg i det minste delvis om et parti av vindturbintårnet (100).23. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor den ene eller flere krantårnseksjonene (20, 30, 40) er sylindriske seksjoner anordnet for å strekke seg om og langsgående langs et parti av vindturbintårnet (100).24. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, som videre inkluderer å koble krantårnekstensjonsseksjonen (30; 40) fast til en tårnseksjon (20; 30) på nedre ende av krantårnet (200).25. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor vindturbintårnet (100) er et offshore-vindturbintårn.26. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor krantårnet (200) som skal forlenges, er forhåndsmontert.27. Fremgangsmåte ifølge et hvilket som helst av de foregående kravene, hvor vindturbintårnet (100) er et offshore-vindturbintårn.28. Apparat for å støtte et krantårn (200) på et vindturbintårn (100), eller på en fundamentseksjon (8) av et vindturbintårn (100), og utføre fremgangsmåten ifølge et hvilket som helst av de foregående kravene, hvor vindturbintårnet (100) eller fundamentseksjonen (8) derav er forsynt med en krantårnbase (10), idet apparatet omfatter:minst én krantårnseksjon (20) for å strekke seg om en vindturbintårnseksjon (2, 3, 4);en krananordning (201) konfigurert til å kobles til og støttes på en øvre ende av den minst ene krantårnseksjonen (20);en løfteanordning (11) for å drive et krantårn (200), inkludert den minst ene krantårnseksjonen (20) og krananordningen (201), langs vindturbintårnet (100) mellom en første, baseposisjon hvori en nedre ende av krantårnet (200) er anordnet ved eller i nærheten av krantårnbasen (10) og en andre, hevet posisjon hvori en nedre ende av krantårnet (200) er hevet langs vindturbintårnet (100) med hensyn til den første posisjonen;støttemiddel (13) for å støtte krantårnet (200) i den andre, hevede posisjonen; ogminst én krantårnekstensjonsseksjon (30, 40) for å strekke seg om en vindturbintårnseksjon (2, 3, 4);hvor løfteanordningen (11) er konfigurert til å drive krantårnet (200), i det minste i en første driftsmodus, bort fra den første posisjonen mot den andre posisjonen for å skape rom til å føre den minst ene krantårnekstensjonsseksjonen (30, 40) f inn i det skapte rommet for å muliggjøre at den minst ene krantårnekstensjonsseksjonen (30, 40) kan anordnes i rommet og kobles til krantårnet (200) for å forlenge krantårnet (200).29. Apparat ifølge krav 28, videre omfattende en krantårnbase (10) konfigurert til å tilveiebringes på vindturbintårnet (100) eller på fundamentseksjonen (8) av vindturbintårnet (100).
Drawings

Priority


16.08.2021 NO 20210981

Patent classes


IPC classesF03D 13/10B66C 23/20F03D 13/25B66C 23/18E04H 12/34CPC classesF03D 13/10B66C 23/207F03D 13/25B66C 23/185E04H 12/345

Citations


US 2010044330 A1 (A1)US 2021207393 A1 (A1)US 2017121998 A1 (A1)US 2015300037 A1 (A1)FR 1428886 A (A)NL 1008402 C (C)

Applicants, owners and inventors


Owners
WIND SPIDER AS
Fabrikkveien 9 4033 STAVANGER NO (STAVANGER Municipality, Rogaland county)Org. number: 925509965
Inventors
Petter Vabø
Ragnhilds gate 78 4044 HAFRSFJORD NO (STAVANGER Municipality, Rogaland county)
Per Olav Haughom
Nedre Høgåsen 18 4440 TONSTAD NO (SIRDAL Municipality, Agder county)

Agent


HÅMSØ PATENTBYRÅ AS
HÅMSØ PATENTBYRÅ AS

Org. number: 918752900

Name and address are automatically synchronized with the Brønnøysund Register Centre.

Open in The Brønnøysund Register Centre
Postboks 9 4068 STAVANGER NO (STAVANGER Municipality, Rogaland county)
Org. number: 918752900
Reference: P30077NO01

Status history


Payment history


Oppositions and appeals


No oppositions or appeals

Administrative limitation


No administrative limitation

Liens and licences


No liens or licenses registered

Gazette entries